Approvals · Stage 6 of 8
Your action
Nothing now
Last update
30 Aug 2026
Control state
IOD awaited · construction not authorised
Immediate next control
Confirm scrutiny position and sanctioned evidence
Attention owner
PMC + Architect

Operational summary only. The controlled register and evidence remain below.

Statutory + project controls

Approvals & Compliance

A professional register that distinguishes submission, scrutiny, approval, sanction and construction permission. It prevents an application or expected approval from being shown to members as if it were already granted.

  • 6 CONTROLLED ITEMS
  • IOD AWAITED
  • CONSTRUCTION NOT AUTHORISED
  1. Municipal building proposal

    Municipal Corporation

    SUBMITTED

    06 Aug 2026

    PMC + Architect

    Next control: Respond to scrutiny observations if raised.

  2. IOD

    Municipal Corporation

    AWAITED

    Pending

    PMC

    Next control: Track scrutiny and obtain documentary evidence of issue.

  3. Sanctioned building plans

    Municipal Corporation

    PENDING

    Pending

    Architect

    Next control: Upload approved drawing set only after sanction.

  4. Commencement permission

    Municipal Corporation

    NOT ISSUED

    Not due

    Developer + PMC

    Next control: Cannot be treated as available before statutory prerequisites.

  5. Fire / life-safety coordination

    Design coordination

    WORKING

    18 Aug 2026

    Architect + MEP

    Next control: Carry requirements into sanction-ready design.

  6. Member PAAA execution readiness

    Society / Developer

    UNDER REVIEW

    30 Aug 2026

    Legal + Developer

    Next control: Close member comments and annexure controls.

Compliance logic

How Nirman should interpret professional evidence.

  1. Submitted ≠ approved

    A submission date confirms filing, not municipal acceptance or sanction.

  2. Working drawing ≠ sanctioned plan

    Internal professional coordination drawings remain working until the sanctioned set is recorded.

  3. IOD ≠ commencement permission

    The system must track each statutory stage independently.

  4. Expected date ≠ evidence

    Forecasts can be shown as forecasts, never as confirmed approvals.

Professional responsibilities

Ownership makes every control actionable.

  1. PMC

    Track municipal process, evidence status and professional follow-up.

  2. Architect

    Maintain versioned plans and sanction-ready design coordination.

  3. Developer

    Support statutory submissions, commercial obligations and readiness evidence.

  4. Society

    Communicate confirmed milestones to members only after evidence is controlled.