Approvals · Stage 6 of 8
Your action
Nothing now
Last update
30 Aug 2026
Control state
NO-GO
Immediate next control
Do not advance until statutory start controls are satisfied
Attention owner
Developer + PMC

Operational summary only. The controlled register and evidence remain below.

Go / no-go project control

Site: Construction Readiness

A professional readiness gate that separates preparation work from actual construction authority. The project can continue coordinating plans, legal documents and mobilisation planning while still remaining firmly NO-GO for demolition or construction.

  • NO-GO
  • 6 HARD GATES BLOCKED
  • CONSTRUCTION NOT AUTHORISED
  • HARD GATES COMPLETE

    0 / 6

    Mandatory statutory, member and financial gates

  • STATUTORY POSITION

    Incomplete

    IOD, sanction and commencement remain open

  • MEMBER HANDOVER

    Not ready

    PAAA under review; no vacating notices

  • PHYSICAL CONSTRUCTION

    Locked

    No demolition or construction authority

CONSTRUCTION DECISION

NO-GO

This is deliberately binary. A project should not show 70% “construction ready” if one mandatory statutory or member-protection gate still prevents lawful/safe commencement.

Readiness logic

Nirman treats mandatory gates as dependencies rather than a cosmetic progress percentage.

  1. Preparation can continue

    Plan coordination, legal review, member data checks and draft mobilisation planning can progress before construction authority.

  2. Physical mobilisation stays locked

    No demolition, possession-based site control or construction start is activated while hard gates remain incomplete.

  3. One blocked hard gate = NO-GO

    The dashboard must not average a missing statutory approval into an attractive percentage.

  4. Gate closure requires evidence

    Each status changes only when the corresponding controlled evidence is recorded.

  1. 01

    IOD / principal permission

    AWAITED
    ACCOUNTABLE OWNER
    PMC

    Mandatory statutory evidence before downstream readiness can advance.

    Evidence today: No issued IOD recorded

  2. 02

    Sanctioned building plans

    PENDING
    ACCOUNTABLE OWNER
    Architect

    Member layouts and site work cannot rely on a working drawing as final.

    Evidence today: Working/submission plans only

  3. 03

    Commencement permission

    NOT ISSUED
    ACCOUNTABLE OWNER
    Developer + PMC

    Construction start remains prohibited.

    Evidence today: No construction commencement evidence

  4. 04

    Member PAAA execution readiness

    UNDER REVIEW
    ACCOUNTABLE OWNER
    Legal + Society

    Member handover cannot be treated as ready while agreements remain open.

    Evidence today: 5 ready for review; 7 still need attention

  5. 05

    Rent + payment protection

    NOT ACTIVATED
    ACCOUNTABLE OWNER
    Developer + Society

    Financial protections must be active before possession handover.

    Evidence today: 0 rent accounts active

  6. 06

    Formal vacating + possession handover

    NOT STARTED
    ACCOUNTABLE OWNER
    Society

    Members remain in possession until formal written instruction and controlled handover.

    Evidence today: 0 written vacating notices

  7. 07

    Site mobilisation / demolition controls

    PLANNED
    ACCOUNTABLE OWNER
    PMC + Developer

    Can be prepared in draft, but cannot be activated before statutory and possession gates.

    Evidence today: Planning only; no mobilisation authority

  8. 08

    Contractor construction mobilisation

    NOT AUTHORISED
    ACCOUNTABLE OWNER
    Developer

    No physical construction mobilisation should be represented as authorised.

    Evidence today: No construction start authority