- Control state
- NO-GO
- Immediate next control
- Do not advance until statutory start controls are satisfied
- Attention owner
- Developer + PMC
Operational summary only. The controlled register and evidence remain below.
Go / no-go project control
Construction Readiness
A professional readiness gate that separates preparation work from actual construction authority. The project can continue coordinating plans, legal documents and mobilisation planning while still remaining firmly NO-GO for demolition or construction.
- NO-GO
- 6 HARD GATES BLOCKED
- CONSTRUCTION NOT AUTHORISED
HARD GATES COMPLETE
0 / 6
Mandatory statutory, member and financial gates
STATUTORY POSITION
Incomplete
IOD, sanction and commencement remain open
MEMBER HANDOVER
Not ready
PAAA under review; no vacating notices
PHYSICAL CONSTRUCTION
Locked
No demolition or construction authority
CONSTRUCTION DECISION
NO-GO
This is deliberately binary. A project should not show 70% “construction ready” if one mandatory statutory or member-protection gate still prevents lawful/safe commencement.
Readiness logic
Nirman treats mandatory gates as dependencies rather than a cosmetic progress percentage.
Preparation can continue
Plan coordination, legal review, member data checks and draft mobilisation planning can progress before construction authority.
Physical mobilisation stays locked
No demolition, possession-based site control or construction start is activated while hard gates remain incomplete.
One blocked hard gate = NO-GO
The dashboard must not average a missing statutory approval into an attractive percentage.
Gate closure requires evidence
Each status changes only when the corresponding controlled evidence is recorded.
- AWAITED
01
IOD / principal permission
Mandatory statutory evidence before downstream readiness can advance.
Evidence today: No issued IOD recorded
- PENDING
02
Sanctioned building plans
Member layouts and site work cannot rely on a working drawing as final.
Evidence today: Working/submission plans only
- NOT ISSUED
03
Commencement permission
Construction start remains prohibited.
Evidence today: No construction commencement evidence
- UNDER REVIEW
04
Member PAAA execution readiness
Member handover cannot be treated as ready while agreements remain open.
Evidence today: 5 ready for review; 7 still need attention
- NOT ACTIVATED
05
Rent + payment protection
Financial protections must be active before possession handover.
Evidence today: 0 rent accounts active
- NOT STARTED
06
Formal vacating + possession handover
Members remain in possession until formal written instruction and controlled handover.
Evidence today: 0 written vacating notices
- PLANNED
07
Site mobilisation / demolition controls
Can be prepared in draft, but cannot be activated before statutory and possession gates.
Evidence today: Planning only; no mobilisation authority
- NOT AUTHORISED
08
Contractor construction mobilisation
No physical construction mobilisation should be represented as authorised.
Evidence today: No construction start authority