- Control state
- IOD awaited · construction not authorised
- Immediate next control
- Confirm scrutiny position and sanctioned evidence
- Attention owner
- PMC + Architect
Operational summary only. The controlled register and evidence remain below.
Statutory + project controls
Pipeline: Approvals & Compliance
A professional register that distinguishes submission, scrutiny, approval, sanction and construction permission. It prevents an application or expected approval from being shown to members as if it were already granted.
- 6 CONTROLLED ITEMS
- IOD AWAITED
- CONSTRUCTION NOT AUTHORISED
- SUBMITTED
Municipal building proposal
06 Aug 2026
PMC + Architect
Next control: Respond to scrutiny observations if raised.
- AWAITED
IOD
Pending
PMC
Next control: Track scrutiny and obtain documentary evidence of issue.
- PENDING
Sanctioned building plans
Pending
Architect
Next control: Upload approved drawing set only after sanction.
- NOT ISSUED
Commencement permission
Not due
Developer + PMC
Next control: Cannot be treated as available before statutory prerequisites.
- WORKING
Fire / life-safety coordination
18 Aug 2026
Architect + MEP
Next control: Carry requirements into sanction-ready design.
- UNDER REVIEW
Member PAAA execution readiness
30 Aug 2026
Legal + Developer
Next control: Close member comments and annexure controls.
Compliance logic
How Nirman should interpret professional evidence.
Submitted ≠ approved
A submission date confirms filing, not municipal acceptance or sanction.
Working drawing ≠ sanctioned plan
Internal professional coordination drawings remain working until the sanctioned set is recorded.
IOD ≠ commencement permission
The system must track each statutory stage independently.
Expected date ≠ evidence
Forecasts can be shown as forecasts, never as confirmed approvals.
Professional responsibilities
Ownership makes every control actionable.
PMC
Track municipal process, evidence status and professional follow-up.
Architect
Maintain versioned plans and sanction-ready design coordination.
Developer
Support statutory submissions, commercial obligations and readiness evidence.
Society
Communicate confirmed milestones to members only after evidence is controlled.