Our redevelopment journey
Our journey
A simple history of the Society redevelopment, from the first formal discussion to the current approvals and PAAA review stage.
- 15 milestones
- Apr 2025 → Aug 2026
- Current stage: approvals
Need to know
- Status
- Stage 6 of 8
- What it means
- Municipal approvals are in progress.
- Your action
- No action required today.
The full record, supporting detail and evidence remain available below.
1 Decision
What happened
12 Apr 2025
Redevelopment formally discussed
Members agreed to begin a structured redevelopment evaluation and appoint professional advisers.
OFFICIAL
2 PMC
What happened
25 May 2025
PMC appointed
Northline Project Advisory was appointed as the Society's project management consultant.
OFFICIAL16 Jun 2025
Architect appointed
Studio Axis Mumbai was appointed to assess planning potential and prepare early redevelopment concepts.
OFFICIAL
3 Tender
What happened
03 Aug 2025
Developer process opened
The Society invited redevelopment proposals against a common commercial and technical brief.
VERIFIED28 Sep 2025
Developer presentations completed
Shortlisted developers presented commercial offers, building concepts and proposed member benefits.
VERIFIED
4 Developer
What happened
19 Oct 2025
Meridian Habitat selected
A Special General Meeting selected Meridian Habitat LLP as the preferred developer.
OFFICIAL14 Nov 2025
Commercial offer consolidated
The Society and developer recorded the main commercial package for agreement drafting.
VERIFIED
5 Development Agreement
What happened
10 Jan 2026
Development Agreement terms settled
Core Society-level redevelopment terms moved from negotiation into final documentation.
VERIFIED21 Feb 2026
Development Agreement executed
The Society and developer executed the Society-level Development Agreement.
OFFICIAL
6 Approvals
What happened
18 Mar 2026
Building concept Version 01 issued
An initial working building concept was circulated for technical review. It was not a sanctioned plan.
VERIFIED29 Apr 2026
Technical review triggered redesign
Parking efficiency, fire movement and structural planning required changes to the first concept.
REPORTED12 Jun 2026
Working Plan Version 02 circulated
A revised working design was shared. Member areas and layouts remained subject to sanction and PAAA.
VERIFIED18 Jul 2026
Parking and amenities reviewed
Members discussed parking configuration and additional amenity requests. Several items remained proposals.
PROPOSED06 Aug 2026
Municipal proposal submitted
The project team recorded submission of the building proposal for the next approval stage.
VERIFIED
Still open at this stage
22 Aug 2026
PAAA draft circulated
A draft member agreement was circulated for member review, comments and member-specific checking.
VERIFIED30 Aug 2026
Member PAAA comments consolidated
Member comments have been grouped for the next legal and developer review. The PAAA remains under revision.
VERIFIED27 Aug 2026
IOD approval still awaited
The PMC reports that the municipal proposal remains in the approval process. No IOD has been recorded as received.
REPORTED
7 Construction
Must be in place before construction
- IOD / principal permissionAWAITEDNo issued IOD recorded
- Sanctioned building plansPENDINGWorking/submission plans only
- Commencement permissionNOT ISSUEDNo construction commencement evidence
- Member PAAA execution readinessUNDER REVIEW5 ready for review; 7 still need attention
- Rent + payment protectionNOT ACTIVATED0 rent accounts active
- Formal vacating + possession handoverNOT STARTED0 written vacating notices
- Site mobilisation / demolition controlsPLANNEDPlanning only; no mobilisation authority
- Contractor construction mobilisationNOT AUTHORISEDNo construction start authority
- 8 Possession
How we reached today
15 milestones
12 Apr 2025
OFFICIALRedevelopment formally discussed
Members agreed to begin a structured redevelopment evaluation and appoint professional advisers.
25 May 2025
OFFICIALPMC appointed
Northline Project Advisory was appointed as the Society's project management consultant.
16 Jun 2025
OFFICIALArchitect appointed
Studio Axis Mumbai was appointed to assess planning potential and prepare early redevelopment concepts.
03 Aug 2025
VERIFIEDDeveloper process opened
The Society invited redevelopment proposals against a common commercial and technical brief.
28 Sep 2025
VERIFIEDDeveloper presentations completed
Shortlisted developers presented commercial offers, building concepts and proposed member benefits.
19 Oct 2025
OFFICIALMeridian Habitat selected
A Special General Meeting selected Meridian Habitat LLP as the preferred developer.
14 Nov 2025
VERIFIEDCommercial offer consolidated
The Society and developer recorded the main commercial package for agreement drafting.
10 Jan 2026
VERIFIEDDevelopment Agreement terms settled
Core Society-level redevelopment terms moved from negotiation into final documentation.
21 Feb 2026
OFFICIALDevelopment Agreement executed
The Society and developer executed the Society-level Development Agreement.
18 Mar 2026
VERIFIEDBuilding concept Version 01 issued
An initial working building concept was circulated for technical review. It was not a sanctioned plan.
29 Apr 2026
REPORTEDTechnical review triggered redesign
Parking efficiency, fire movement and structural planning required changes to the first concept.
12 Jun 2026
VERIFIEDWorking Plan Version 02 circulated
A revised working design was shared. Member areas and layouts remained subject to sanction and PAAA.
18 Jul 2026
PROPOSEDParking and amenities reviewed
Members discussed parking configuration and additional amenity requests. Several items remained proposals.
06 Aug 2026
VERIFIEDMunicipal proposal submitted
The project team recorded submission of the building proposal for the next approval stage.
22 Aug 2026
VERIFIEDPAAA draft circulated
A draft member agreement was circulated for member review, comments and member-specific checking.