Our redevelopment journey

Our journey

A simple history of the Society redevelopment, from the first formal discussion to the current approvals and PAAA review stage.

  • 15 milestones
  • Apr 2025 → Aug 2026
  • Current stage: approvals

Need to know

Status
Stage 6 of 8
What it means
Municipal approvals are in progress.
Your action
No action required today.

The full record, supporting detail and evidence remain available below.

  1. 1 DecisionDone

    What happened

    1. 12 Apr 2025

      Redevelopment formally discussed

      Members agreed to begin a structured redevelopment evaluation and appoint professional advisers.

      OFFICIAL
  2. 2 PMCDone

    What happened

    1. 25 May 2025

      PMC appointed

      Northline Project Advisory was appointed as the Society's project management consultant.

      OFFICIAL
    2. 16 Jun 2025

      Architect appointed

      Studio Axis Mumbai was appointed to assess planning potential and prepare early redevelopment concepts.

      OFFICIAL
  3. 3 TenderDone

    What happened

    1. 03 Aug 2025

      Developer process opened

      The Society invited redevelopment proposals against a common commercial and technical brief.

      VERIFIED
    2. 28 Sep 2025

      Developer presentations completed

      Shortlisted developers presented commercial offers, building concepts and proposed member benefits.

      VERIFIED
  4. 4 DeveloperDone

    What happened

    1. 19 Oct 2025

      Meridian Habitat selected

      A Special General Meeting selected Meridian Habitat LLP as the preferred developer.

      OFFICIAL
    2. 14 Nov 2025

      Commercial offer consolidated

      The Society and developer recorded the main commercial package for agreement drafting.

      VERIFIED
  5. 5 Development AgreementDone

    What happened

    1. 10 Jan 2026

      Development Agreement terms settled

      Core Society-level redevelopment terms moved from negotiation into final documentation.

      VERIFIED
    2. 21 Feb 2026

      Development Agreement executed

      The Society and developer executed the Society-level Development Agreement.

      OFFICIAL
  6. 6 ApprovalsYou are here

    What happened

    1. 18 Mar 2026

      Building concept Version 01 issued

      An initial working building concept was circulated for technical review. It was not a sanctioned plan.

      VERIFIED
    2. 29 Apr 2026

      Technical review triggered redesign

      Parking efficiency, fire movement and structural planning required changes to the first concept.

      REPORTED
    3. 12 Jun 2026

      Working Plan Version 02 circulated

      A revised working design was shared. Member areas and layouts remained subject to sanction and PAAA.

      VERIFIED
    4. 18 Jul 2026

      Parking and amenities reviewed

      Members discussed parking configuration and additional amenity requests. Several items remained proposals.

      PROPOSED
    5. 06 Aug 2026

      Municipal proposal submitted

      The project team recorded submission of the building proposal for the next approval stage.

      VERIFIED

    Still open at this stage

    1. 22 Aug 2026

      PAAA draft circulated

      A draft member agreement was circulated for member review, comments and member-specific checking.

      VERIFIED
    2. 30 Aug 2026

      Member PAAA comments consolidated

      Member comments have been grouped for the next legal and developer review. The PAAA remains under revision.

      VERIFIED
    3. 27 Aug 2026

      IOD approval still awaited

      The PMC reports that the municipal proposal remains in the approval process. No IOD has been recorded as received.

      REPORTED
  7. 7 ConstructionLaterNext: Not yet scheduled

    Must be in place before construction

    • IOD / principal permissionAWAITEDNo issued IOD recorded
    • Sanctioned building plansPENDINGWorking/submission plans only
    • Commencement permissionNOT ISSUEDNo construction commencement evidence
    • Member PAAA execution readinessUNDER REVIEW5 ready for review; 7 still need attention
    • Rent + payment protectionNOT ACTIVATED0 rent accounts active
    • Formal vacating + possession handoverNOT STARTED0 written vacating notices
    • Site mobilisation / demolition controlsPLANNEDPlanning only; no mobilisation authority
    • Contractor construction mobilisationNOT AUTHORISEDNo construction start authority
  8. 8 PossessionLater

How we reached today

15 milestones
  1. 12 Apr 2025

    OFFICIAL

    Redevelopment formally discussed

    Members agreed to begin a structured redevelopment evaluation and appoint professional advisers.

  2. 25 May 2025

    OFFICIAL

    PMC appointed

    Northline Project Advisory was appointed as the Society's project management consultant.

  3. 16 Jun 2025

    OFFICIAL

    Architect appointed

    Studio Axis Mumbai was appointed to assess planning potential and prepare early redevelopment concepts.

  4. 03 Aug 2025

    VERIFIED

    Developer process opened

    The Society invited redevelopment proposals against a common commercial and technical brief.

  5. 28 Sep 2025

    VERIFIED

    Developer presentations completed

    Shortlisted developers presented commercial offers, building concepts and proposed member benefits.

  6. 19 Oct 2025

    OFFICIAL

    Meridian Habitat selected

    A Special General Meeting selected Meridian Habitat LLP as the preferred developer.

  7. 14 Nov 2025

    VERIFIED

    Commercial offer consolidated

    The Society and developer recorded the main commercial package for agreement drafting.

  8. 10 Jan 2026

    VERIFIED

    Development Agreement terms settled

    Core Society-level redevelopment terms moved from negotiation into final documentation.

  9. 21 Feb 2026

    OFFICIAL

    Development Agreement executed

    The Society and developer executed the Society-level Development Agreement.

  10. 18 Mar 2026

    VERIFIED

    Building concept Version 01 issued

    An initial working building concept was circulated for technical review. It was not a sanctioned plan.

  11. 29 Apr 2026

    REPORTED

    Technical review triggered redesign

    Parking efficiency, fire movement and structural planning required changes to the first concept.

  12. 12 Jun 2026

    VERIFIED

    Working Plan Version 02 circulated

    A revised working design was shared. Member areas and layouts remained subject to sanction and PAAA.

  13. 18 Jul 2026

    PROPOSED

    Parking and amenities reviewed

    Members discussed parking configuration and additional amenity requests. Several items remained proposals.

  14. 06 Aug 2026

    VERIFIED

    Municipal proposal submitted

    The project team recorded submission of the building proposal for the next approval stage.

  15. 22 Aug 2026

    VERIFIED

    PAAA draft circulated

    A draft member agreement was circulated for member review, comments and member-specific checking.