Vacating readiness

When do we move out?

Members should continue living normally. Vacating will only happen after the required approvals, member documentation, financial protections and a formal written Society instruction are in place.

  • DO NOT VACATE
  • NO DATE ANNOUNCED
  • FORMAL NOTICE REQUIRED

Need to know

Status
Do not vacate
What it means
No move-out date has been announced. Approvals, documents and protections must come first.
Your action
Continue living normally.

The full record, supporting detail and evidence remain available below.

  • IOD / key municipal approval

    AWAITED

    Approval process still underway

  • Sanctioned plan

    PENDING

    Working plan is not final

  • Member PAAA

    UNDER REVIEW

    Member-specific wording being checked

  • Rent + payment protection

    NOT YET ACTIVATED

    Must be ready before handover

  • Formal vacating notice

    NOT ISSUED

    No member should vacate without it

  • Handover of existing flat

    NOT STARTED

    Occurs only after formal readiness

What must happen first

The portal treats vacating as a controlled sequence, not as a single verbal date.
  1. Approvals become sufficiently ready

    Key municipal permission and the sanctioned building position must be recorded.

  2. Your member documentation is ready

    The final member agreement should accurately record the flat, area, money and protection terms.

  3. Financial protections are activated

    Transit rent, PDC/payment protection and shifting arrangements should be ready before handover.

  4. The Society issues a written instruction

    The final vacating notice should state the action date and handover procedure clearly.

What you can do meanwhile

Useful preparation without acting before the project is ready.
  1. Keep your current address and contact details updated with the Society.

  2. Do not sign a private handover or vacating letter that is not part of the approved Society process.

  3. Start considering temporary-location preferences only when the formal timeline becomes reasonably clear.

  4. Check that rent, escalation, PDC and shifting-support terms match your final member agreement before handover.