Project assurance
Risks: Risk & Issues
A live professional risk register that separates uncertainty from fact. Each risk records severity, likelihood, impact, accountable owner, evidence, trigger and mitigation so project teams can act before a concern becomes a member-facing problem.
- 4 MONITORED RISKS
- 0 CRITICAL
- 1 HIGH
CRITICAL
0
No critical uncontrolled risk
HIGH
1
Approval timetable uncertainty
MEDIUM
2
PAAA + parking controls
LOW
1
Contained historical record issue
- HIGH
RSK-014
Approval timetable uncertainty
IOD not yet recorded as issued
Trigger / early warningMunicipal scrutiny extends beyond current planning assumption.Mitigation / controlMaintain evidence-led approval tracking; do not activate vacating or construction workflows against forecast dates.
- MEDIUM
RSK-015
PAAA version-control mismatch
Member comments consolidated; final controlled member version pending
Trigger / early warningDifferent member drafts or annexures circulate without one current controlled version.Mitigation / controlUse one version register, member-specific exception log and issue history before execution.
- MEDIUM
RSK-016
Working parking scheme may change
Parking remains a working scheme and no member slot is final
Trigger / early warningSanction or technical coordination changes the working parking mix.Mitigation / controlKeep member allocation disabled until approved plan basis and final allocation process are recorded.
- LOW
RSK-017
Historical project-record inconsistency
Fictional archival record clarification remains pending
Trigger / early warningAn older record conflicts with the current controlled project register.Mitigation / controlKeep the item isolated, record source evidence and prevent it from altering member status unless formally validated.
Risk heat map
Illustrative concentration of the current fictional professional risk register.
| LOW IMPACT | MEDIUM IMPACT | HIGH IMPACT | |
|---|---|---|---|
| LIKELY | PAAA VERSION CONTROL | APPROVAL TIMETABLE | |
| POSSIBLE | PARKING CHANGE | ||
| UNLIKELY | RECORD INCONSISTENCY |
Escalation rules
When a risk should move from professional monitoring into formal governance.
Escalate immediately
Any risk that can invalidate member instructions, statutory readiness or financial protection.
Escalate at threshold
Schedule risk that crosses an agreed milestone or requires a formal project-plan change.
Communicate to members
Only when the risk creates a real member consequence or a confirmed project-position change.
Close only with evidence
A risk is not closed merely because the team expects the issue to resolve.